Yale W-CSC Shared Collection Phase II

TITLE: Yale W-CSC Shared Collection Phase II BUDGET: $1.2 Million May 2023 – June 2024 This project was located in West Haven, CT. Scope of work included but was not limited to Renovations and Additions to the Art Collections Shared Storage building at Yale West...

Munson Street New Haven

TITLE: Munson Street BUDGET: $7.8 Million DATE: May 2022 – December 2023 This project was located in New Haven, CT. Former Winchester Arms and Olin Manufacturing site. Work included but was not limited to 100,00 CY contaminated soil remediation and complete site...

Tweed New Haven Airport Terminal Renovation

TITLE: Tweed New Haven Airport Terminal Renovation BUDGET: $1.9 Million DATE: September 2021 – December 2021 This project was located at the Tweed New Haven Airport and was part of the phased construction project of terminal renovations and runway expansion....

Trout Brook Trail

TITLE: Trout Brook Trail, Phase 5 BUDGET: $690,000 DATE: October 2021 – April 2022 The Trout Brook Trail is West Hartford’s long-term greenway project that provides walkers, runners, and bicyclists a safe, enjoyable route to exercise and explore. This eight to...

Rehabilitation of Paper Mill Road Bridge

TITLE: Rehabilitation of Paper Mill Road Bridge No. 05528 Over Jeremy River BUDGET: $325,000 DATE: May 2020 – November 2020 The Project consisted of removing the existing bridge superstructure, construction new concrete bridge seats on existing concrete/masonry...

Old Field Creek Hydraulic Dredging Project

TITLE: Old Field Creek Hydraulic Dredging Project BUDGET: $968,000 DATE: August 2020 – December 2020 The Project was located in West Haven at Old Field Creek between Beach Street and Blohm Street and Marshall Street, and seeks to remove accumulated contaminated...