TITLE: Tweed New Haven Airport Terminal Renovation
BUDGET: $1.9 Million
DATE: September 2021 – December 2021
This project was located at the Tweed New Haven Airport and was part of the phased construction project of terminal renovations and runway expansion. Giordano was the sitework contractor for this portion of the project. Scope of work included but not limited to erosion controls, site demolition, earthwork, soil management, dewatering, utility work, site concrete, sidewalks & curbs, exterior upgrades, storm detention swale enlargement, asphalt paving, pavement markings, signage, & permanent fencing. Additional Photos:Phone